1
GATE ME 2024
MCQ (Single Correct Answer)
+1
-0.33

A set of jobs $U, V, W, X, Y, Z$ arrive at time $t = 0$ to a production line consisting of two workstations in series. Each job must be processed by both workstations in sequence (i.e., the first followed by the second). The process times (in minutes) for each job on each workstation in the production line are given below.

JobUVWXYZ
Workstation 1573468
Workstation 2466857

The sequence in which the jobs must be processed by the production line if the total makespan of production is to be minimized is

A

W-X-Z-V-Y-U

B

W-X-V-Z-Y-U

C

W-U-Z-V-Y-X

D

U-Y-V-Z-X-W

GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
CBSE
Class 12