1
GATE EE 2007
MCQ (Single Correct Answer)
+2
-0.6
The total reactance and total susceptance of a lossless overhead $$EHV$$ line, operating at $$50$$ $$Hz,$$ are given by $$0.045$$ pu and $$1.2$$ pu respectively. If the velocity of wave propagation is $$3\,\, \times \,\,{10^5}$$ km/s, then the approximate length of line is
A
$$122$$ $$km$$
B
$$172$$ $$km$$
C
$$222$$ $$km$$
D
$$272$$ $$km$$
2
GATE EE 2007
MCQ (Single Correct Answer)
+2
-0.6
Single line diagram of a $$4$$-bus single source distribution system is shown below. Branches $${e_1},\,\,$$ $${e_2},\,\,$$ $${e_3}\,\,$$ and $${e_4}\,\,$$ have equal impedences. The load current values indicated in the figure are in per unit. GATE EE 2007 Power System Analysis - Parameters and Performance of Transmission Lines Question 7 English

Distribution Company's policy requires radial system operation with minimum loss. This can be achieved by opening of the branch

A
$${e_1}$$
B
$${e_2}$$
C
$${e_3}$$
D
$${e_4}$$
3
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
The $$A, B, C, D$$ constant of a $$220$$ $$kV$$ line are:
$$A = D = 0.94\,\angle \,10,\,\,\,B = 130\,\angle \,730,\,\,\,C = 0.001\,\angle \,900.\,\,$$ If the sending end voltage of the line for a given load delivered at nominal voltage is $$240$$ $$kV$$, the % voltage regulation of the line is
A
$$5$$
B
$$9$$
C
$$16$$
D
$$21$$
4
GATE EE 2005
MCQ (Single Correct Answer)
+2
-0.6
At an industrial sub-station with a $$4$$ $$MW$$ load, a capacitor of $$2$$ MVAR is installed to maintain the load power factor at $$0.97$$ lagging. If the capacitor goes out of service, the load power factor becomes
A
$$0.85$$ lag
B
$$1.00$$ lag
C
$$0.80$$ lag
D
$$0.90$$ lag
GATE EE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12