1
GATE EE 2004
MCQ (Single Correct Answer)
+2
-0.6
A 500 kVA, 3-phase transformer has iron loses of 300 W and full load copper losses of 600 W. The percentage load at which the transformer is expected to have maximum efficiency is
A
50.0%
B
70.7%
C
141.4%
D
200.0%
2
GATE EE 2004
MCQ (Single Correct Answer)
+2
-0.6
A 50 kVA, 3300/230 V single-phase transformers is connected as an autotransformer shown in figure. The nominal rating of the autotransformer will be GATE EE 2004 Electrical Machines - Transformers Question 54 English
A
50.0 kVA
B
53.5 kVA
C
717.4 kVA
D
767.4 kVA
3
GATE EE 2003
MCQ (Single Correct Answer)
+2
-0.6
Figure shows an ideal single-phase transformer. The primary and secondary coils are wound on the core as shown. Turns ratio $$\left(\frac{N_1}{N_2}\right)$$=2. The correct phasors of voltages $$E_1,\;E_2$$ currents $$I_1,\;I_2$$ and core flux $$\phi$$ are as shown in GATE EE 2003 Electrical Machines - Transformers Question 52 English
A
GATE EE 2003 Electrical Machines - Transformers Question 52 English Option 1
B
GATE EE 2003 Electrical Machines - Transformers Question 52 English Option 2
C
GATE EE 2003 Electrical Machines - Transformers Question 52 English Option 3
D
GATE EE 2003 Electrical Machines - Transformers Question 52 English Option 4
4
GATE EE 2003
MCQ (Single Correct Answer)
+2
-0.6
Figure shows a $$\triangle$$ - Y connected 3-phase distribution transformer used to step down the voltage from 11000 V to 415 V line-to line. It has two switches S1 and S2. Under normal conditions S1 is closed and S2 is open. Under certain special conditions S1 is open and S2 is closed. In such a case the magnitude of the voltage across the LV terminals a and c is GATE EE 2003 Electrical Machines - Transformers Question 50 English
A
240 V
B
480 V
C
415 V
D
0 V