GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
A $$300$$ $$kVA$$ transformer has $$95\% $$ efficiency at full load $$0.8$$ $$pf$$ lagging and $$96\% $$ efficiency at half load, unity $$pf.$$
What is the maximum efficiency (in %) at unity $$pf$$ load?
2
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
A $$300$$ $$kVA$$ transformer has $$95\% $$ efficiency at full load $$0.8$$ $$pf$$ lagging and $$96\% $$ efficiency at half load, unity $$pf.$$
The iron loss $$\left( {{P_i}} \right)$$ in $$kW,$$ under full load operation are
3
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
Two transformers are to be operated in parallel such that they share load in proportion to their $$kVA$$ ratings. The rating of the first transformer is $$500$$ $$kVA$$ and its $$pu$$ leakage impedance is $$0.05$$ $$pu.$$ If the rating of second transformer is $$250$$ $$kVA,$$ its $$pu$$ leakage impedance is
4
GATE EE 2004
MCQ (Single Correct Answer)
+2
-0.6
The resistance and reactance of a 100 kVA 11000|400 V, $$\triangle$$ - Y distribution
transformer are 0.02 and 0.07 pu respectively. The phase impedance of the
transformer referred to the primary is
GATE EE Subjects
Browse all chapters by subject
Electric Circuits
Electrical Machines
Engineering Mathematics
Signals and Systems
Power Electronics
Power System Analysis
Digital Electronics
Analog Electronics
Electromagnetic Fields
Control Systems
Electrical and Electronics Measurement
General Aptitude