1
GATE EE 2009
MCQ (Single Correct Answer)
+2
-0.6
Three generators are feeding a load of $$100$$ $$MW$$. The details of the generators Rating, Efficiency and Regulation are shown below GATE EE 2009 Power System Analysis - Power Generation Cost Question 10 English

In the event of increased load power demand, which of the following will happen?

A
All the generators will share equal power
B
Generator-$$3$$ will share more power compared to Generator-$$1$$
C
Generator-$$1$$ will share more power compared to Generator-$$2$$
D
Generator-2 will share more power compared to Generator-$$3$$
2
GATE EE 2008
MCQ (Single Correct Answer)
+2
-0.6
A lossless power system has to serve a load of $$250$$ $$MW.$$ There are two generators ($$G1$$ and $$G2$$) in the system with cost curves $${C_1}$$ and $${C_2}$$ respectively defined as follows:
$${C_1}\left( {{P_{G1}}} \right) = {P_{G1}} + 0.055 \times P_{G1}^2$$
$${C_2}\left( {{P_{G2}}} \right) = 3{P_{G2}} + 0.03 \times P_{G2}^2$$
Where $${P_{G1}}$$ and $${P_{G2}}$$ are the MW injections from generator $${G_1}$$ and $${G_2}$$ respectively. Thus, the minimum cost dispatch will be
A
$${P_{G1}} = 250\,MW;\,\,{P_{G2}} = 0\,MW$$
B
$${P_{G1}} = 150\,MW;\,\,{P_{G2}} = 100\,MW$$
C
$${P_{G1}} = 100\,MW;\,\,{P_{G2}} = 150\,MW$$
D
$${P_{G1}} = 0\,MW;\,\,{P_{G2}} = 250\,MW$$
3
GATE EE 2005
MCQ (Single Correct Answer)
+2
-0.6
A load centre is at an equidistant from the two thermal generating stations $${G_1}$$ and $${G_2}$$ as shown in figure. The fuel cost characteristics of the generating stations are given by
$${F_1} = a + b{P_1} + cP_1^2\,Rs/hour$$
$${F_2} = a + b{P_2} + 2cP_2^2\,Rs/hour$$ GATE EE 2005 Power System Analysis - Power Generation Cost Question 12 English

Where $${P_1}$$ and $${P_2}$$ are the generations in $$MW$$ of $${G_1}$$and $${G_2}$$, respectively. For most economic generation to meet $$300MW$$ of load $${P_1}$$ and $${P_2},$$ respectively, are

A
$$150, 150$$
B
$$100, 200$$
C
$$200, 100$$
D
$$175, 125$$
4
GATE EE 2003
MCQ (Single Correct Answer)
+2
-0.6
Incremental fuel costs (in some appropriate unit) for a power plant consisting of three generating units are
$${\rm I}{C_1} = 20 + 0.3\,\,{P_1},\,{\rm I}{C_2} = 30 + 0.4\,\,{P_2},\,{\rm I}{C_3} = 30$$
Assume that all the three units are operating all the time. Minimum and maximum loads on each unit are $$50$$ $$MW$$ and $$300$$ $$MW$$ respectively. If the plant is operating on economic load dispatch to supply the total power demand of $$700$$ $$MW$$, the power generated by each unit is
A
$${P_1} = 242.86MW;{P_2} = 157.14MW;$$ and $${P_3} = 300MW$$
B
$${P_1} = 157.14MW;{P_2} = 242.86MW;$$ and $${P_3} = 300MW$$
C
$${P_1} = 300.00MW;{P_2} = 300.00MW;$$ and $${P_3} = 100MW$$
D
$${P_1} = 242.86MW;{P_2} = 157.14MW;$$ and $${P_3} = 100MW$$
GATE EE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12