1
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
For a power system the admittance and impedance matrices for the fault studies are as follows. $$$\eqalign{ & {Y_{bus}} = \left[ {\matrix{ { - j8.75} & {j1.25} & {j2.50} \cr {j1.25} & { - j6.25} & {j2.50} \cr {j2.50} & {j2.50} & { - j5.00} \cr } } \right] \cr & {Z_{bus}} = \left[ {\matrix{ {j0.16} & {j0.08} & {j0.12} \cr {j0.08} & {j0.24} & {j0.16} \cr {j0.12} & {j0.16} & {j0.34} \cr } } \right] \cr} $$$

The pre-fault voltages are $$1.0$$ $$p.u.$$ at all the buses. The system was unloaded prior to the fault. A solid $$3$$ phase fault takes place at bus $$2.$$

The per unit fault feeds from generators connected to buses $$1$$ and $$2$$ respectively are

A
$$1.20, 2.51$$
B
$$1.55, 2.61$$
C
$$1.66, 2.50$$
D
$$5.00,2.50$$
2
GATE EE 2005
MCQ (Single Correct Answer)
+2
-0.6
The network shown in the given figure has impedances in p.u. as indicated. The diagonal element $$Y22$$ of the bus admittance matrix $${Y_{BUS}}$$ of the network is GATE EE 2005 Power System Analysis - Load Flow Studies Question 17 English
A
$$-j$$ $$19.8$$
B
$$+j$$ $$20.0$$
C
$$+j$$ $$0.2$$
D
$$-j$$ $$19.95$$
3
GATE EE 2003
MCQ (Single Correct Answer)
+2
-0.6
The bus impedance matrix of a $$4$$-bus power system is given by $$${Z_{bus}} = \left[ {\matrix{ {j0.3435} & {j0.2860} & {j0.2723} & {j0.277} \cr {j0.2860} & {j0.3408} & {j0.2586} & {j0.2414} \cr {j0.2723} & {j0.2586} & {j0.2791} & {j0.2209} \cr {j0.2277} & {j0.2414} & {j0.2209} & {j0.2791} \cr } } \right]$$$

A branch having an impedance of $$j0.2\Omega $$ is connected between bus $$2$$ and the reference. Then the values of $${Z_{22,new}}$$ and $${Z_{23,new}}$$ of the bus impedance matrix of the modified network are respectively

A
$$j0.5408\,\Omega \,\,\,$$ and $$\,\,\,j0.4586\,\Omega $$
B
$$j0.1260\,\Omega \,\,\,$$ and $$\,\,\,j0.0956\,\Omega $$
C
$$j0.5408\,\Omega \,\,\,$$ and $$\,\,\,j0.0956\,\Omega $$
D
$$j0.1260\,\Omega \,\,\,$$ and $$\,\,\,j0.1630\,\Omega $$
4
GATE EE 2002
MCQ (Single Correct Answer)
+2
-0.6
A power system consists of 2 areas (Area 1 and Area 2) connected by a single tie line (figure). It is required to carry out a load flow study on this system. While entering the network data, the tie-line data (connectivity and parameters) is inadvertently left out. If the load flow program is run with this incomplete data. GATE EE 2002 Power System Analysis - Load Flow Studies Question 19 English
A
The load-flow will converge only if the slack bus is specified in Area 1
B
The load-flow will converge only if the slack bus is specified in Area 2
C
The load-flow will converge if the slack bus is specified in either Area 1 or Area 2
D
The load-flow will not converge if only one slack bus is specified.
GATE EE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12