1
GATE EE 2011
MCQ (Single Correct Answer)
+2
-0.6
A three–bus network is shown in the figure below indicating the p.u. impedances of each element GATE EE 2011 Power System Analysis - Load Flow Studies Question 12 English

The bus admittance matrix, $$Y$$-$$bus,$$ of the network is

A
$$j\left[ {\matrix{ {0.3} & { - 0.2} & 0 \cr { - 0.2} & {0.12} & {0.08} \cr 0 & {0.08} & {0.02} \cr } } \right]$$
B
$$j\left[ {\matrix{ { - 15} & 5 & 0 \cr 5 & {7.5} & { - 12.5} \cr 0 & { - 12.5} & {2.5} \cr } } \right]$$
C
$$j\left[ {\matrix{ {0.1} & {0.2} & 0 \cr {0.2} & {0.12} & { - 0.08} \cr 0 & { - 0.08} & {0.10} \cr } } \right]$$
D
$$j\left[ {\matrix{ { - 10} & 5 & 0 \cr 5 & {7.5} & {12.5} \cr 0 & {12.5} & { - 10} \cr } } \right]$$
2
GATE EE 2009
MCQ (Single Correct Answer)
+2
-0.6
For the $${Y_{bus}}$$ matrix of a $$4$$-bus system given in per unit, the buses having shunt elements are $$${Y_{BUS}} = j\left[ {\matrix{ { - 5} & 2 & {2.5} & 0 \cr 2 & { - 10} & {2.5} & 4 \cr {2.5} & {2.5} & { - 9} & 4 \cr 0 & 4 & 4 & { - 8} \cr } } \right]$$$
A
$$3$$ and $$4$$
B
$$2$$ and $$3$$
C
$$1$$ and $$2$$
D
$$1,2$$ and $$4$$
3
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
The Gauss Seidel load flow method has following disadvantages. Tick the incorrect student.
A
Unreliable convergence
B
Slow convergence
C
Choice of slack bus effects convergence
D
A good initial guess for voltages is essential for convergence
4
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
For a power system the admittance and impedance matrices for the fault studies are as follows. $$$\eqalign{ & {Y_{bus}} = \left[ {\matrix{ { - j8.75} & {j1.25} & {j2.50} \cr {j1.25} & { - j6.25} & {j2.50} \cr {j2.50} & {j2.50} & { - j5.00} \cr } } \right] \cr & {Z_{bus}} = \left[ {\matrix{ {j0.16} & {j0.08} & {j0.12} \cr {j0.08} & {j0.24} & {j0.16} \cr {j0.12} & {j0.16} & {j0.34} \cr } } \right] \cr} $$$

The pre-fault voltages are $$1.0$$ $$p.u.$$ at all the buses. The system was unloaded prior to the fault. A solid $$3$$ phase fault takes place at bus $$2.$$

The per unit fault feeds from generators connected to buses $$1$$ and $$2$$ respectively are

A
$$1.20, 2.51$$
B
$$1.55, 2.61$$
C
$$1.66, 2.50$$
D
$$5.00,2.50$$
GATE EE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12