GATE EE 2002
MCQ (Single Correct Answer)
+2
-0.6
A power system consists of 2 areas (Area 1 and Area 2) connected by a single tie line (figure). It is required to carry out a load flow study on this system. While entering the network data, the tie-line data (connectivity and parameters) is inadvertently left out. If the load flow program is run with this incomplete data. GATE EE 2002 Power System Analysis - Load Flow Studies Question 20 English
A
The load-flow will converge only if the slack bus is specified in Area 1
B
The load-flow will converge only if the slack bus is specified in Area 2
C
The load-flow will converge if the slack bus is specified in either Area 1 or Area 2
D
The load-flow will not converge if only one slack bus is specified.