1
GATE ME 2015 Set 3
Numerical
+2
-0
Ratio of solidification time of a cylindrical casting (height $$=$$ radius) to that of a cubic casting of side two times the height of cylindrical casting is ____________
Your input ____
2
GATE ME 2015 Set 2
Numerical
+2
-0
A cube and a sphere made of cast iron (each of volume $$1000\,\,c{m^3}$$) were cast under identical conditions. The time taken for solidifying the cube was $$4$$ $$s.$$ The solidification time (in $$s$$) for the sphere is _____________________
Your input ____
3
GATE ME 2014 Set 1
Numerical
+2
-0
An aluminium alloy (density $$2600$$ $$kg/{m^3}$$ ) casting is to be produced. A cylindrical hole of $$100$$ $$mm$$ diameter and $$100$$ $$mm$$ length is made in the casting using sand core (density $$1600$$ $$kg/{m^3}$$ ). The net buoyancy force (in Newton) acting on the core is _____________________
Your input ____
4
GATE ME 2014 Set 4
Numerical
+2
-0
A cylindrical riser of $$6$$ $$cm$$ diameter and $$6$$ $$cm$$ height has to be designed for a sand casting mould for producing a steel rectangular plate casting of $$7cm \times 10cm \times 2cm$$ dimensions having the total solidification time of $$1.36$$ minute. The total solidification time (in minute) of the riser is ___________________
Your input ____
GATE ME Subjects
Browse all chapters by subject
Production Engineering
General Aptitude
Fluid Mechanics
Heat Transfer
Thermodynamics
Engineering Mechanics
Machine Design
Industrial Engineering
Strength of Materials
Engineering Mathematics
Theory of Machines
Turbo Machinery