1
GATE ME 2007
MCQ (Single Correct Answer)
+2
-0.6
A $$200$$ $$mm$$ long down sprue has an area of cross section of $$650$$ $$m{m^2}$$ where the pouring basin meets the down sprue (i.e. at the beginning of the down sprue). A constant head of molten metal is maintaining by the pouring basin. The molten metal flow rate is $$6.5 \times {10^5}\,\,\,m{m^3}/s.$$ considering the end of down sprue to be open to atmosphere and an acceleration due to gravity of $${10^4}mm/{s^2},$$ the area of the down sprue in $$m{m^2}$$ at its end (avoiding aspiration effects) should be GATE ME 2007 Production Engineering - Casting Question 32 English
A
$$650$$
B
$$350$$
C
$$290.7$$
D
$$190.0$$
2
GATE ME 2007
MCQ (Single Correct Answer)
+2
-0.6
Volume of a cube of a side $$''l''$$ and volume of sphere of radius $$' r '$$ are equal. Both the cube and the sphere are solid and same material. They are being cast. The ratio of the solidification time of the cube to the same of the sphere is
A
$${\left( {4\pi /6} \right)^3}.{\left( {r/l} \right)^6}$$
B
$$\left( {4\pi /6} \right).{\left( {r/l} \right)^2}$$
C
$$\left( {4\pi /6} \right).{\left( {r/l} \right)^3}$$
D
$${\left( {4\pi /6} \right)^2}.{\left( {r/l} \right)^4}$$
3
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
In a sand casting operation, the total liquid head is maintained constant such that it is equal to the mould height. The time taken to fill the mould with a top gate is $${t_A}.$$ If the same mould is filed with a bottom gate, then the time taken is $${t_B}.$$ Ignore the time required to fill the runner and frictional effects. Assume atmospheric pressure at the top molten metal surfaces. The relation between the $${t_A}$$ and $${t_B}$$ is
A
$${t_B} = \sqrt 2 .{t_A}$$
B
$${t_B} = 2.{t_A}$$
C
$${t_B} = {{{t_A}} \over {\sqrt 2 }}$$
D
$${t_B} = 2\sqrt 2 .{t_A}$$
4
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
A mould has a downsprue whose length is $$20$$ $$cm$$ and the cross sectional area at the base of the down sprue is $$1\,\,c{m^2}.$$ The down sprue feeds a horizontal runner leading into the mould cavity of volume $$1000\,\,c{m^3}.$$ The time required to fill the mould cavity will be
A
$$4.05$$ s
B
$$5.05$$ s
C
$$6.05$$ s
D
$$7.25$$ s
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12