1
GATE ME 2007
MCQ (Single Correct Answer)
+2
-0.6
A $$200$$ $$mm$$ long down sprue has an area of cross section of $$650$$ $$m{m^2}$$ where the pouring basin meets the down sprue (i.e. at the beginning of the down sprue). A constant head of molten metal is maintaining by the pouring basin. The molten metal flow rate is $$6.5 \times {10^5}\,\,\,m{m^3}/s.$$ considering the end of down sprue to be open to atmosphere and an acceleration due to gravity of $${10^4}mm/{s^2},$$ the area of the down sprue in $$m{m^2}$$ at its end (avoiding aspiration effects) should be GATE ME 2007 Production Engineering - Casting Question 28 English
A
$$650$$
B
$$350$$
C
$$290.7$$
D
$$190.0$$
2
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
In a sand casting operation, the total liquid head is maintained constant such that it is equal to the mould height. The time taken to fill the mould with a top gate is $${t_A}.$$ If the same mould is filed with a bottom gate, then the time taken is $${t_B}.$$ Ignore the time required to fill the runner and frictional effects. Assume atmospheric pressure at the top molten metal surfaces. The relation between the $${t_A}$$ and $${t_B}$$ is
A
$${t_B} = \sqrt 2 .{t_A}$$
B
$${t_B} = 2.{t_A}$$
C
$${t_B} = {{{t_A}} \over {\sqrt 2 }}$$
D
$${t_B} = 2\sqrt 2 .{t_A}$$
3
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
A mould has a downsprue whose length is $$20$$ $$cm$$ and the cross sectional area at the base of the down sprue is $$1\,\,c{m^2}.$$ The down sprue feeds a horizontal runner leading into the mould cavity of volume $$1000\,\,c{m^3}.$$ The time required to fill the mould cavity will be
A
$$4.05$$ s
B
$$5.05$$ s
C
$$6.05$$ s
D
$$7.25$$ s
4
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
Match List - $${\rm I}$$ (products) with List - $${\rm II}$$ (casting process) and select the correct answer using the codes given below the lists GATE ME 2005 Production Engineering - Casting Question 4 English
A
$$A - 3,\,\,B - 2,\,\,C - 4,\,\,D - 5$$
B
$$A - 1,\,\,B - 3,\,\,C - 4,\,\,D - 5$$
C
$$A - 1,\,\,B - 2,\,\,C - 3,\,\,D - 4$$
D
$$A - 3,\,\,B - 2,\,\,C - 5,\,\,D - 4$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
CBSE
Class 12