The figure shows an incomplete schematic of a conventional lathe to be used for cutting threads with different pitches. The speed gear box $${U_v}$$ is shown and the feed gear box $${U_s}$$ is to be placed. $$P,Q,R$$ and $$S$$ denote locations and have no other significance. Changes in $${U_v}$$ should $$NOT$$ affect the pitch of thread being cut and changes in $${U_s}$$ should NOT affect the cutting speed. GATE ME 2008 Production Engineering - Machining Question 6 English

The correct connections and the correct placement of $${U_s}$$ are given below

A
$$Q$$ & $$E$$ are connected. Us is place between $$P$$ and $$Q$$
B
$$S$$ & $$E$$ are connected. Us is place between $$R$$ and $$S$$
C
$$Q$$ & $$E$$ are connected. Us is place between $$Q$$ and $$E$$
D
$$S$$ & $$E$$ are connected. Us is place between $$S$$ and $$E$$
2
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
If each abrasive grain is viewed as a cutting tool, then which of the following represents the cutting parameters in common grinding operations?
A
Large negative rake angle, low shear angle and high cutting speed
B
Large positive rake angle, low shear angle and high cutting speed
C
Large negative rake angle, high shear angle and low cutting speed
D
Zero rake angle, high shear angle and high cutting speed
3
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
A $$600$$ $$mm$$ $$ \times \,\,30\,\,mm$$ flat surface of a plate is to be finish machined on a shaper. The plate has been fixed with the $$600$$ $$mm$$ side along the tool travel direction. If the tool over-travel at each end of the plate is $$20$$ $$mm,$$ average cutting speed is $$8$$ $$m/min,$$ feed rate is $$0.3$$ $$mm/stroke$$ and the ratio of return time to cutting time of the tool is $$1:2,$$ the time required for machining will be
A
$$8$$ minutes
B
$$12$$ minutes
C
$$16$$ minutes
D
$$20$$ minutes
4
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
Through holes of $$10$$ $$mm$$ diameter are to be drilled in steel plate of $$20$$ $$mm$$ thickness. Drill spindle speed is $$300$$ $$rpm,$$ feed $$0.2$$ $$mm/rev$$ and drill point angle is $${120^0}.$$ Assuming drill over travel of $$2mm$$ the time for producing a hole will be
A
$$4$$ seconds
B
$$25$$ seconds
C
$$100$$ seconds
D
$$110$$ seconds
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12