1
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
In a single pass drilling operation, a through hole of $$15$$ $$mm$$ diameter is to be drilled in a steel plate of $$50$$ $$mm$$ thickness. Drill spindle speed is $$500$$ $$rpm,$$ feed is $$0.2$$ $$mm/rev$$ and drill point angle is $${118^ \circ }.$$ Assuming $$2$$ $$mm$$ clearance at approach and exit, the total drill time (in seconds) is
2
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
The figure shows an incomplete schematic of a conventional lathe to be used for cutting threads with different pitches. The speed gear box $${U_v}$$ is shown and the feed gear box $${U_s}$$ is to be placed. $$P,Q,R$$ and $$S$$ denote locations and have no other significance. Changes in $${U_v}$$ should $$NOT$$ affect the pitch of thread being cut and changes in $${U_s}$$ should NOT affect the cutting speed.
The correct connections and the correct placement of $${U_s}$$ are given below
3
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
If each abrasive grain is viewed as a cutting tool, then which of the following represents the cutting parameters in common grinding operations?
4
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
A $$600$$ $$mm$$ $$ \times \,\,30\,\,mm$$ flat surface of a plate is to be finish machined on a shaper. The plate has been fixed with the $$600$$ $$mm$$ side along the tool travel direction. If the tool over-travel at each end of the plate is $$20$$ $$mm,$$ average cutting speed is $$8$$ $$m/min,$$ feed rate is $$0.3$$ $$mm/stroke$$ and the ratio of return time to cutting time of the tool is $$1:2,$$ the time required for machining will be
GATE ME Subjects
Browse all chapters by subject
Production Engineering
General Aptitude
Fluid Mechanics
Heat Transfer
Thermodynamics
Engineering Mechanics
Machine Design
Industrial Engineering
Strength of Materials
Engineering Mathematics
Theory of Machines
Turbo Machinery