1
GATE ME 1990
MCQ (Single Correct Answer)
+2
-0.6
In the Rankine cycle when super-heated steam is used:
A
Thermal efficiency increases
B
Steam consumption decreases
C
Steam dryness after expansion increases
D
All of the above
2
GATE ME 1990
MCQ (Single Correct Answer)
+2
-0.6
When initially dry and saturated steam flows through a nozzle, the ratio of actual discharge to calculated discharge is
A
Equal to $$1.0$$
B
Greater than $$1.0$$
C
Less than $$1.0$$
D
Independent of inlet conditions
3
GATE ME 1989
Fill in the Blanks
+2
-0
The fundamental objective of employing the condenser in a steam power plant is to (reducce / increase ) the ______________of steam
4
GATE ME 1989
MCQ (Single Correct Answer)
+2
-0.6
A economizer in a steam generator performs the function of
A
Preheating the combustion air
B
Preheating the feed water
C
Preheating the input fuel
D
Raising the temperature of steam
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
CBSE
Class 12