1
GATE ME 1997
Subjective
+5
-0
A water turbine delivering $$10$$ $$MW$$ power is to be tested with the help of a geometrically similar $$1:8$$ model, which runs at the same speed as the proto-type.

(a) Find the power developed by the model assuming the efficiencies of the model and the proto-type are equal.

(b) Find the ratio of the heads and the ratio of mass flow rates between the proto-type and the model.

2
GATE ME 1996
Subjective
+5
-0
In a hydroelectric station, water is available at the rate of $$175{m^3}/s$$ under a head of $$18m.$$ The turbines run at a speed of $$150$$ $$rpm$$ with overall efficiency of $$82\% $$. Find the number of turbines required if they have the maximum specific speed of $$460.$$
3
GATE ME 1992
Subjective
+5
-0
A Hydro turbine is required to give $$25$$ $$MW$$ at $$50$$ $$m$$ head and $$90$$ $$rpm$$ runner speed. The laboratory facilities available, permit testing of $$20$$ $$kW$$ models at $$5$$ $$m$$ head. What should be the model runner speed and model to prototype scale ratio?
4
GATE ME 1991
Subjective
+5
-0
A $$7MW$$ hydro turbine working under a head of $$10$$ $$m$$ at a rotational speed of $$125$$ $$rpm$$ is to be designed and developed by conducting model tests in a laboratory. Maximum possible discharge to the model is $$600$$ liters per second at a constant head of $$5m.$$ Determine the minimum scale of the model and its speed if the expected efficiency of the model is $$85\% .$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12