1
GATE ME 1992
Subjective
+5
-0
A Hydro turbine is required to give $$25$$ $$MW$$ at $$50$$ $$m$$ head and $$90$$ $$rpm$$ runner speed. The laboratory facilities available, permit testing of $$20$$ $$kW$$ models at $$5$$ $$m$$ head. What should be the model runner speed and model to prototype scale ratio?
2
GATE ME 1991
Subjective
+5
-0
A $$7MW$$ hydro turbine working under a head of $$10$$ $$m$$ at a rotational speed of $$125$$ $$rpm$$ is to be designed and developed by conducting model tests in a laboratory. Maximum possible discharge to the model is $$600$$ liters per second at a constant head of $$5m.$$ Determine the minimum scale of the model and its speed if the expected efficiency of the model is $$85\% .$$
3
GATE ME 1990
Subjective
+5
-0
Identify the type of turbo machinery for the following case. Specify the reasons.
Power developed $$=430$$ $$kW;$$
Operating head $$=300$$ $$m;$$
Speed $$=600$$ $$rpm.$$