1
GATE ME 2016 Set 1
MCQ (Single Correct Answer)
+1
-0.3
The part of a gating system which regulates the rate of pouring of molten metal is
A
pouring basin
B
runner
C
choke
D
ingate
2
GATE ME 2015 Set 3
MCQ (Single Correct Answer)
+1
-0.3
In full mould (cavity-less) casting process, the Pattern is made of
A
Expanded polystyrene
B
Wax
C
Epoxy
D
Plaster of Paris
3
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+1
-0.3
Match the casting defects (Group A) with the probable causes (Group B): GATE ME 2014 Set 3 Production Engineering - Casting Question 48 English
A
$$P - 1,\,\,Q - 3,\,\,R - 2,\,\,S - 4$$
B
$$P - 4,\,\,Q - 3,\,\,R - 2,\,\,S - 1$$
C
$$P - 3,\,\,Q - 4,\,\,R - 2,\,\,S - 1$$
D
$$P - 1,\,\,Q - 2,\,\,R - 4,\,\,S - 3$$
4
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+1
-0.3
The hot tearing in a metal casting is due to
A
high fluidity
B
high melt temperature
C
Wide range of solidification temperature
D
Low coefficient of thermal expansion
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12