1
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+1
-0.3
Match the casting defects (Group A) with the probable causes (Group B): GATE ME 2014 Set 3 Production Engineering - Casting Question 48 English
A
$$P - 1,\,\,Q - 3,\,\,R - 2,\,\,S - 4$$
B
$$P - 4,\,\,Q - 3,\,\,R - 2,\,\,S - 1$$
C
$$P - 3,\,\,Q - 4,\,\,R - 2,\,\,S - 1$$
D
$$P - 1,\,\,Q - 2,\,\,R - 4,\,\,S - 3$$
2
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+1
-0.3
The hot tearing in a metal casting is due to
A
high fluidity
B
high melt temperature
C
Wide range of solidification temperature
D
Low coefficient of thermal expansion
3
GATE ME 2013
MCQ (Single Correct Answer)
+1
-0.3
A cube shaped casting solidifies in $$5$$ min. The solidification time in min for a cube of the same material, which is $$8$$ times heavier than the original casting, will be
A
$$10$$
B
$$20$$
C
$$24$$
D
$$40$$
4
GATE ME 2011
MCQ (Single Correct Answer)
+1
-0.3
Green sand mould indicates that
A
Polymeric mould has been cured
B
Mould has been totally dried
C
Mould is green in colour
D
Mould contains moisture
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12