1
GATE EE 2007
MCQ (Single Correct Answer)
+1
-0.3
The incremental cost curves in Rs/MWhr for two generators supplying a common load of $$700$$ MW are shown in the figures. The maximum and minimum generation limits are also indicated. The optimum generation schedule is: GATE EE 2007 Power System Analysis - Power Generation Cost Question 16 English
A
Generator A : $$400$$ MW,
Generator B : $$300$$ MW
B
Generator A : $$350$$ MW,
Generator B : $$350$$ MW
C
Generator A : $$450$$ MW,
Generator B : $$250$$ MW
D
Generator A : $$425$$ MW,
Generator B : $$275$$ MW
2
GATE EE 1995
MCQ (Single Correct Answer)
+1
-0.3
In order to have a lower cost of electrical energy generation,
A
The load factor and diversity factor should be low
B
The load factor should be low but diversity factor should be high
C
The load factor should be high but diversity factor should be low
D
The load factor and diversity factor should be high