1
GATE EE 2022
Numerical
+1
-0.33
If only 5% of the supplied power to a cable reaches the output terminal, the power loss in the cable, in decibels, is ______. (round off to nearest integer).
Your input ____
2
GATE EE 2022
MCQ (Single Correct Answer)
+1
-0.33

The fuel cost functions in rupees/hour for two 600 MW thermal power plants are given by

Plant 1 : C1 = 350 + 6P1 + 0.004P$$_1^2$$

Plant 2 : C2 = 450 + aP2 + 0.003P$$_2^2$$

where P1 and P2 are power generated by plant 1 and plant 2, respectively, in MW and a is constant. The incremental cost of power ($$\lambda$$) is 8 rupees per MWh. The two thermal power plants together meet a total power demand of 550 MW. The optimal generation of plant 1 and plant 2 in MW, respectively, are

A
200, 350
B
250, 300
C
325, 225
D
350, 200
3
GATE EE 2012
MCQ (Single Correct Answer)
+1
-0.3
The figure shows a two-generator system supplying a load of $${P_D} = 40\,MW,$$ connected at bus $$2.$$ GATE EE 2012 Power System Analysis - Power Generation Cost Question 15 English

The fuel cost of generators $${G_1}$$ and $${G_2}$$ are: $${C_1}\left( {{P_{G1}}} \right) = 10,000\,\,Rs/MWhr$$ and $${C_2}\left( {{P_{G2}}} \right) = 12,500\,\,Rs/MWhr$$ and the loss in the line is $$\,{P_{loss(pu)}} = 0.5\,\,P_{G1\left( {pu} \right),}^2\,\,\,\,$$ where the loss coefficient is specified in pu on a $$100$$ $$MVA$$ base. The most economic power generation schedule in $$MW$$ is

A
$${P_{G1}} = 20,\,{P_{G2}} = 22$$
B
$${P_{G1}} = 22,\,{P_{G2}} = 20$$
C
$${P_{G1}} = 20,\,{P_{G2}} = 22$$
D
$${P_{G1}} = 0,\,{P_{G2}} = 40$$
4
GATE EE 2007
MCQ (Single Correct Answer)
+1
-0.3
The incremental cost curves in Rs/MWhr for two generators supplying a common load of $$700$$ MW are shown in the figures. The maximum and minimum generation limits are also indicated. The optimum generation schedule is: GATE EE 2007 Power System Analysis - Power Generation Cost Question 16 English
A
Generator A : $$400$$ MW,
Generator B : $$300$$ MW
B
Generator A : $$350$$ MW,
Generator B : $$350$$ MW
C
Generator A : $$450$$ MW,
Generator B : $$250$$ MW
D
Generator A : $$425$$ MW,
Generator B : $$275$$ MW