GATE ME 1993
MCQ (Single Correct Answer)
+2
-0.6
Round the clock cooling of an apartment having a load of $$300$$ $$MJ/day$$ requires and air-conditioning plant of capacity about
A
$$1$$ ton
B
$$5$$ tons
C
$$10$$ tons
D
$$100$$ tons