A cyclic heat engine does $$50$$ $$kJ$$ of work per cycle. If the efficiency of the heat engine is $$75\% $$, then heat rejected per cycle is
A
$$16{2 \over 3}\,kJ$$
B
$$33{1 \over 3}\,kJ$$
C
$$37{1 \over 2}\,kJ$$
D
$$66{2 \over 3}\,kJ$$
2
GATE ME 1996
MCQ (Single Correct Answer)
+2
-0.6
A solar energy based heat engine which receives $$80$$ $$kJ$$ of heat at $${100^ \circ }C$$ and rejects $$70$$ $$kJ$$ of heat to the ambient at $${30^ \circ }C$$ is to be designed. The thermal efficiency of the heat engine is
A
$$70\% $$
B
$$18.8\% $$
C
$$12.5\% $$
D
Indeterminate
3
GATE ME 1996
MCQ (Single Correct Answer)
+2
-0.6
For two cycles coupled in series, the topping cycle has an efficiency of $$30\% $$ and the bottoming cycle has an efficiency of $$20\% $$. The overall combined cycle efficiency is
A
$$50\% $$
B
$$44\% $$
C
$$38\% $$
D
$$55\% $$
4
GATE ME 1993
MCQ (Single Correct Answer)
+2
-0.6
Round the clock cooling of an apartment having a load of $$300$$ $$MJ/day$$ requires and air-conditioning plant of capacity about
A
$$1$$ ton
B
$$5$$ tons
C
$$10$$ tons
D
$$100$$ tons
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
CBSE
Class 12