1
GATE ME 1993
MCQ (Single Correct Answer)
+1
-0.3
In $$DC$$ welding, the straight polarity (electrode negative) results in
A
Lower penetration
B
Lower deposition rate
C
Less heating of work piece
D
Smaller weld pod
2
GATE ME 1992
Fill in the Blanks
+1
-0
In an explosive welding process, the ..................... (maximum/minimum) velocity of impact is fixed by the velocity of sound in the ............. (flyer / target) plate material.
3
GATE ME 1992
MCQ (Single Correct Answer)
+1
-0.3
For resistance spot welding of $$1.5$$ $$mm$$ thick steel sheets, the current required is of the order
A
$$10$$ $$Amp$$
B
$$100$$ $$Amp$$
C
$$1000$$ $$Amp$$
D
$$10,000$$ $$Amp$$
4
GATE ME 1991
MCQ (Single Correct Answer)
+1
-0.3
For gas welding a particular job using a neutral oxy-acetylene flame the acetylene consumption was $$10$$ ltrs. The oxygen consumption from the cylinder in liters will be
A
$$5$$
B
$$10$$
C
$$15$$
D
$$20$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12