1
GATE CSE 2005
MCQ (Single Correct Answer)
+2
-0.6
Consider the following code fragment:
if (fork() == 0)
{
   a = a + 5;
   printf("%d, %d \n", a, &a);
}
else
{
   a = a - 5;
   printf ("%d, %d \n", a, &a);
}

Let $$u,v$$ be the values printed by the parent process, and $$x,y$$ be the values printed by the child process. Which one of the following is TRUE?
A
$$u=x+10$$ and $$v=y$$
B
$$u=x+10$$ and $$v \ne y$$
C
$$u+10=x$$ and $$v=y$$
D
$$u+10=x$$ and $$v \ne y$$
2
GATE CSE 2004
MCQ (Single Correct Answer)
+2
-0.6
Consider the following set of processes, with the arrival times and the $$CPU$$-burst times given in milliseconds. GATE CSE 2004 Operating Systems - Process Concepts and Cpu Scheduling Question 31 English

What is the average turnaround time for these processes with the preemptive shortest remaining processing time first $$(SRTF)$$ algorithm?

A
$$5.50$$
B
$$5.75$$
C
$$6.00$$
D
$$6.25$$
3
GATE CSE 2003
MCQ (Single Correct Answer)
+2
-0.6
A uni-processor computer system only has two processes, both of which alternate $$10$$ $$ms$$ $$CPU$$ bursts with $$90$$ $$ms$$ $${\rm I}/O$$ bursts. Both the processes were created at nearly the same time. The $${\rm I}/O$$ of both processes can proceed in parallel. Which of the following scheduling strategies will result in the least $$CPU$$ utilization (over a long period of time) for this system?
A
First come First served scheduling
B
Shortest remaining time first scheduling
C
Static priority scheduling with different priorities for the two processes
D
Round robin scheduling with a time quantum of $$5$$ $$ms.$$
4
GATE CSE 2002
MCQ (Single Correct Answer)
+2
-0.6
Which combination of the following features will suffice to characterize an $$OS$$ as a multi-programmed $$OS?$$
$$(a).$$ More than one program may be loaded into main memory at the same time for execution.
$$(b).$$ If a program waits for certain events such as $$I/O$$, another program is immediately scheduled for execution.
$$(c).$$ If the execution of a program terminates, another program is immediately scheduled for execution.
A
$$a$$
B
$$a$$ and $$b$$
C
$$a$$ and $$c$$
D
$$a, b$$ and $$c$$
GATE CSE Subjects
Software Engineering
Web Technologies
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12