1
GATE CSE 2005
MCQ (Single Correct Answer)
+2
-0.6
Consider the following code fragment:
if (fork() == 0)
{
   a = a + 5;
   printf("%d, %d \n", a, &a);
}
else
{
   a = a - 5;
   printf ("%d, %d \n", a, &a);
}

Let $$u,v$$ be the values printed by the parent process, and $$x,y$$ be the values printed by the child process. Which one of the following is TRUE?
A
$$u=x+10$$ and $$v=y$$
B
$$u=x+10$$ and $$v \ne y$$
C
$$u+10=x$$ and $$v=y$$
D
$$u+10=x$$ and $$v \ne y$$
2
GATE CSE 2004
MCQ (Single Correct Answer)
+2
-0.6
Consider the following set of processes, with the arrival times and the $$CPU$$-burst times given in milliseconds. GATE CSE 2004 Operating Systems - Process Concepts and Cpu Scheduling Question 34 English

What is the average turnaround time for these processes with the preemptive shortest remaining processing time first $$(SRTF)$$ algorithm?

A
$$5.50$$
B
$$5.75$$
C
$$6.00$$
D
$$6.25$$
3
GATE CSE 2003
MCQ (Single Correct Answer)
+2
-0.6
A uni-processor computer system only has two processes, both of which alternate $$10$$ $$ms$$ $$CPU$$ bursts with $$90$$ $$ms$$ $${\rm I}/O$$ bursts. Both the processes were created at nearly the same time. The $${\rm I}/O$$ of both processes can proceed in parallel. Which of the following scheduling strategies will result in the least $$CPU$$ utilization (over a long period of time) for this system?
A
First come First served scheduling
B
Shortest remaining time first scheduling
C
Static priority scheduling with different priorities for the two processes
D
Round robin scheduling with a time quantum of $$5$$ $$ms.$$
4
GATE CSE 2002
MCQ (Single Correct Answer)
+2
-0.6
Which combination of the following features will suffice to characterize an $$OS$$ as a multi-programmed $$OS?$$
$$(a).$$ More than one program may be loaded into main memory at the same time for execution.
$$(b).$$ If a program waits for certain events such as $$I/O$$, another program is immediately scheduled for execution.
$$(c).$$ If the execution of a program terminates, another program is immediately scheduled for execution.
A
$$a$$
B
$$a$$ and $$b$$
C
$$a$$ and $$c$$
D
$$a, b$$ and $$c$$
GATE CSE Subjects
Software Engineering
Web Technologies
EXAM MAP