1
GATE CSE 2007
MCQ (Single Correct Answer)
+2
-0.6
An operating system uses Shortest Remaining Time first $$(SRT)$$ process scheduling algorithm. Consider the arrival times and execution times for the following processes: GATE CSE 2007 Operating Systems - Process Concepts and Cpu Scheduling Question 25 English

What is the total waiting time for process $$P2?$$

A
$$5$$
B
$$15$$
C
$$40$$
D
$$55$$
2
GATE CSE 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider three processes, all arriving at time zero, with total execution time of $$10,20,$$ and $$30$$ units, respectively. Each process spends the first $$20$$% of execution time doing $${\rm I}/O$$, the next $$70$$% of time doing computation, and the last $$10$$% of time doing $${\rm I}/O$$ again. The operating system uses a shortest remaining compute time first scheduling algorithm and scheduling a new process either when the running processes gets blocked on $${\rm I}/O$$ or when the running process finishes its compute burst. Assume that all $${\rm I}/O$$ operations can be overlapped as much as possible. For what percentage of time does the $$CPU$$ remain idle?
A
$$0$$%
B
$$10.6$$%
C
$$30.0$$%
D
$$89.4$$%
3
GATE CSE 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider three processes (process id $$0,1,2,$$ respectively) with compute time bursts $$2, 4,$$ and $$8$$ time units. All processes arrive at time zero. Consider the longest remaining time first $$(LRTF)$$ scheduling algorithm. In $$LRTF$$ ties are broken by giving priority to the process with the lowest process id. The average turn around time is
A
$$13$$ units
B
$$14$$ units
C
$$15$$ units
D
$$16$$ units
4
GATE CSE 2005
MCQ (Single Correct Answer)
+2
-0.6
Consider the following code fragment:
if (fork() == 0)
{
   a = a + 5;
   printf("%d, %d \n", a, &a);
}
else
{
   a = a - 5;
   printf ("%d, %d \n", a, &a);
}

Let $$u,v$$ be the values printed by the parent process, and $$x,y$$ be the values printed by the child process. Which one of the following is TRUE?
A
$$u=x+10$$ and $$v=y$$
B
$$u=x+10$$ and $$v \ne y$$
C
$$u+10=x$$ and $$v=y$$
D
$$u+10=x$$ and $$v \ne y$$
GATE CSE Subjects
Software Engineering
Web Technologies
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12