1
GATE ME 1992
MCQ (Single Correct Answer)
+1
-0.3
A condenser of a refrigeration system rejects heat at a rate of $$120$$ $$kW,$$ while its compressor consumes a power of $$30$$ $$kW.$$ The coefficient of performance of the system would be
A
$$1/4$$
B
$$4$$
C
$$1/3$$
D
$$3$$