1
GATE EE 2016 Set 1
Numerical
+1
-0
The magnitude of three-phase fault currents at buses A and B of a power system are 10 pu and 8 pu, respectively. Neglect all resistances in the system and consider the pre-fault system to be unloaded. The pre-fault voltage at all buses in the system is 1.0 pu. The voltage magnitude at bus B during a three-phase fault at bus A is 0.8 pu. The voltage magnitude at bus A during a three-phase fault at bus B in pu, is __________.
Your input ____
2
GATE EE 2016 Set 1
MCQ (Single Correct Answer)
+1
-0.3
In a 100 bus power system, there are 10 generators. In a particular iteration of Newton Raphson load flow technique (in polar coordinates), two of the PV buses are converted to PQ type. In this iteration.
A
the number of unknown voltage angles increases by two and the number of unknown voltage magnitudes increases by two.
B
the number of unknown voltage angles remains unchanged and the number of unknown voltage magnitudes increases by two.
C
the number of unknown voltage angles increases by two and the number of unknown voltage magnitudes decreases by two.
D
the number of unknown voltage angles remains unchanged and the number of unknown voltage magnitudes decreases by two
3
GATE EE 2015 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A $$3$$-bus power system network consists of $$3$$ transmission lines. The bus admittance matrix of the uncompensated system is
$$\left[ {\matrix{ { - j6} & {j3} & {j4} \cr {j3} & { - j7} & {j5} \cr {j4} & {j5} & { - j8} \cr } } \right]\,pu$$
If the shunt capacitance of all transmission lines is $$50$$% compensated, the imaginary part of the $$3$$rd row $$3$$rd column element (in $$pu$$) of the bus admittance matrix after compensation is
A
$$-j7.0$$
B
$$-j8.5$$
C
$$-j7.5$$
D
$$-j9.0$$
4
GATE EE 2014 Set 3
Numerical
+1
-0
A 183-bus power system has 150PQ buses and 32 PV buses. In the general case, to obtain the load flow solution using Newton-Raphson method in polar coordinates, the minimum number of simultaneous equations to be solved is ___________.
Your input ____
GATE EE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12