1
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
In a $$CNC$$ program block, $$N002\,\,\,\,G02\,\,\,\,G91\,\,\,\,X40\,\,\,\,Z40....,\,\,\,\,G02\,\,\,\,\& \,\,\,\,G91$$ refer to
A
Circular interpolation in counterclockwise direction and incremental dimension
B
Circular interpolation in counterclockwise direction and absolute dimension
C
Circular interpolation in clockwise direction and incremental dimension
D
Circular interpolation in clockwise direction and absolute dimension
2
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Match the following GATE ME 2009 Production Engineering - Advance Machine Tools Question 11 English
A
$$P - 2,\,\,Q - 3,\,\,R - 4,\,\,S - 1$$
B
$$P - 3,\,\,Q - 4,\,\,R - 1,\,\,S - 2$$
C
$$P - 3,\,\,Q - 4,\,\,R - 2,\,\,S - 1$$
D
$$P - 4,\,\,Q - 3,\,\,R - 2,\,\,S - 1$$
3
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
In the feed drive of a point to point open loop $$CNC$$ drive, a stepper motor rotating at $$200steps/rev$$ drives a table through a gear box and lead screw-nut mechanism (pitch $$=4mm,$$ number of starts $$=1$$). The gear ratio $$=$$ Output speed / input speed is given by $$U=1/4.$$ The stepper motor (driven by voltage pulses from a pulse generator) executes $$1$$ step / pulse from a pulse generator) executes $$1$$ step / pulse of the generator. The frequency of the pulse train from the pulse generator is $$f=10000$$ pulses per minute. GATE ME 2008 Production Engineering - Advance Machine Tools Question 10 English

The basic length unit $$(BLU)$$, i.e. the table movement corresponding to $$1$$ pulse of the pulse generator

A
$$0.5$$ microns
B
$$5$$ Microns
C
$$50$$ Microns
D
$$500$$ Microns
4
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
In the feed drive of a point to point open loop $$CNC$$ drive, a stepper motor rotating at $$200steps/rev$$ drives a table through a gear box and lead screw-nut mechanism (pitch $$=4mm,$$ number of starts $$=1$$). The gear ratio $$=$$ Output speed / input speed is given by $$U=1/4.$$ The stepper motor (driven by voltage pulses from a pulse generator) executes $$1$$ step / pulse from a pulse generator) executes $$1$$ step / pulse of the generator. The frequency of the pulse train from the pulse generator is $$f=10000$$ pulses per minute. GATE ME 2008 Production Engineering - Advance Machine Tools Question 9 English

A customer insists on a modification to change the $$BLU$$ of the $$CNC$$ drive to $$10$$ Microns without changing the table speed. The modification can be accomplished by

A
Changing $$U$$ to $${\raise0.5ex\hbox{$\scriptstyle 1$} \kern-0.1em/\kern-0.15em \lower0.25ex\hbox{$\scriptstyle 2$}}$$ and reducing $$f$$ to $$f/2$$
B
Changing $$U$$ to $$1/8$$ and increasing $$f$$ to $$2f$$
C
Changing $$U$$ to $${\raise0.5ex\hbox{$\scriptstyle 1$} \kern-0.1em/\kern-0.15em \lower0.25ex\hbox{$\scriptstyle 2$}}$$ and keeping $$f$$ unchanged
D
Keeping $$U$$ unchanged and increasing $$f$$ to $$2f$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12