1
GATE EE 2000
Subjective
+5
-0
For the configuration shown in figure, the breaker connecting a large system to bus $$2$$ is initially open. The system $$3$$-phase fault level at bus $$3$$ under this condition is not known. After closing the system breaker, the $$3$$-phase fault level at bus $$1$$ was found to be $$5.0$$ p.u. What will be the new $$3$$-phase fault level at system bus $$3,$$ after the interconnection? All per unit values are on common base. Prefault load currents are neglected and prefault voltages are assumed to be $$1.0$$ p.u. at all buses. GATE EE 2000 Power System Analysis - Symmetrical Components and Symmetrical and Unsymmetrical Faults Question 7 English
2
GATE EE 1999
Subjective
+5
-0
Determine the required MVA rating of the circuit breaker CB for the system shown in given figure. Consider the grid as infinite bus. Choose 6 MVA as base. Transformer 3-phase, 33/11 kV, 6 MVA, 0.01+j0.08 p.u. impedance. Load 3-phase 11 kV, 5800 kVA, 0.8 lag, j0.2 p.u. impedance. Impedance of each feeder 9+j 18 $$\Omega $$. GATE EE 1999 Power System Analysis - Symmetrical Components and Symmetrical and Unsymmetrical Faults Question 8 English
3
GATE EE 1999
Subjective
+5
-0
Determine the magnitudes of the symmetrical components ($${{{\rm I}_{R1}},\,{{\rm I}_{R2}}\,}$$ and $${{{\rm I}_{R0}}}$$) of the currents in a three phase (RYB) three wire system, when a short circuit occurs between R and Y phase wires, the fault current being 100 A.
4
GATE EE 1994
True or False
+5
-0
In a power-system, the $$3$$-phase fault MVA is always higher than the single-line-ground fault MVA at a bus (State True or False)
A
TRUE
B
FALSE
GATE EE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12