1
GATE EE 2005
MCQ (Single Correct Answer)
+2
-0.6
Two wattmeter's, which are connected to measure the total power on a three-phase system supplying a balanced load, read $$10.5$$ $$kW$$ and $$–2.5$$ $$kW$$ respectively. The total power and the power factor respectively are
A
$$13.0$$ $$kW,$$ $$0.334$$
B
$$13.0$$ $$kW,$$ $$0.684$$
C
$$8.0$$ $$kW,$$ $$0.52$$
D
$$8.0$$ $$kW,$$ $$0.334$$
2
GATE EE 2004
MCQ (Single Correct Answer)
+2
-0.6
A single-phase load is connected between $$R$$ and $$Y$$ terminals of a $$415$$ $$V,$$ symmetrical, $$3$$-phase, $$4$$-wire system with phase sequence $$RYB$$. A wattmeter is connected in the system as shown in figure. The power factor of the load is $$0.8 $$ lagging. The wattmeter will read GATE EE 2004 Electrical and Electronics Measurement - Measurement of Energy and Power Question 12 English
A
$$-795$$ $$W$$
B
$$-597$$ $$W$$
C
$$+597$$ $$W$$
D
$$+795$$ $$W$$
3
GATE EE 2004
MCQ (Single Correct Answer)
+2
-0.6
A dc A-h meter is rated for 15 A, 250V. The meter constant is 14.4 A-sec/rev. The meter constant at rated voltage may be expressed as
A
3750 rev/kWh
B
3600 rev/kWh
C
1000 rev/kWh
D
960 rev/kWh
4
GATE EE 2003
MCQ (Single Correct Answer)
+2
-0.6
The voltage-flux adjustment of a certain $$1$$-phase $$220$$ $$V$$ induction watt-hour meter is altered so that the phase angle between the applied voltage and the flux due to it $${85^0}$$ (instead of $${90^0}$$). The errors introduced in the reading of this meter when the current is $$5$$ $$A$$ at power factors of unity and $$0.5$$ lagging are respectively
A
$$3.8$$ $$mW,$$ $$77.4$$ $$mW$$
B
$$-3.8$$ $$mW,$$ $$-77.4$$ $$mW$$
C
$$-4.2$$ $$W,$$ $$-85.1$$ $$W$$
D
$$4.2$$ $$W,$$ $$85.1$$ $$W$$
GATE EE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12