1
GATE CSE 1999
MCQ (Single Correct Answer)
+2
-0.6
For the schedule given below, which of the following is correct: GATE CSE 1999 Database Management System - Transactions and Concurrency Question 25 English
A
This schedule is serialized and can occur in a scheme using 2PL protocol
B
This schedule is serializable but cannot occur in a scheme using 2PL protocol
C
This schedule is not serializable but can occur in a scheme using 2PL protocol
D
This schedule is not serializable and cannot occur in a scheme using 2PL protocol.
GATE CSE Subjects
Software Engineering
Web Technologies
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12