For the schedule given below, which of the following is correct: GATE CSE 1999 Database Management System - Transactions and Concurrency Question 29 English
A
This schedule is serialized and can occur in a scheme using 2PL protocol
B
This schedule is serializable but cannot occur in a scheme using 2PL protocol
C
This schedule is not serializable but can occur in a scheme using 2PL protocol
D
This schedule is not serializable and cannot occur in a scheme using 2PL protocol.