1
GATE CSE 2012
MCQ (Single Correct Answer)
+2
-0.6
Consider the following transactions with data items P and Q initialized to zero:
T1 : read (P) ; 
     read (Q) ; 
     if P = 0 then Q : = Q + 1 ; 
     write (Q). 
T2 : read (Q) ; 
     read (P) 
     if Q = 0 then P : = P + 1 ; 
     write (P).
Any non-serial interleaving of T1 and T2 for concurrent execution leads to
A
a serializable schedule
B
a schedule that is not conflict serializable
C
a conflict serializable schedule
D
a schedule for which precedence graph cannot be drawn
2
GATE CSE 2010
MCQ (Single Correct Answer)
+2
-0.6
Consider the following schedule for transactions T1, T2 and T3: GATE CSE 2010 Database Management System - Transactions and Concurrency Question 21 English Which one of the schedules below is the correct serialization of the above?
A
$$T1 \to T3 \to T2$$
B
$$T2 \to T1 \to T3$$
C
$$T2 \to T3 \to T1$$
D
$$T3 \to T1 \to T2$$
3
GATE CSE 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider two transactions T1 and T2 and four schedules S1, S2, S3, S4 of T1 and T2 as given below:

T1: R1[ x ] W1[ x ] W1[ y ]
T2: R2[ x ] R2[ y ] W2[ y ]
S1: R1[ x ] R2[ x ] R2[ y ] W1[ x ] W1[ y ] W2[ y ]
S2: R1[ x ] R2[ x ] R2[ y ] W1[ x ] W2[ y ] W1[ y ]
S3: R1[ x ] W1[ x ] R2[ x ] W1[ y ] R2[ y ] W2[ y ]
S4: R2[ x ] R2[ y ] R1[ x ] W1[ x ] W1[ y ] W2[ y ]

Which of the above schedules are conflict-serializable?
A
S1 and S2
B
S2 and S3
C
S3 only
D
S4 only
4
GATE CSE 2009
MCQ (Single Correct Answer)
+2
-0.6
Let R and S be relational schemes such that R = { a, b, c } and S = { c }. Now consider the following queries on the database:

I. $$\pi_{R-S}(r) - \pi_{R-S} \left (\pi_{R-S} (r) \times s - \pi_{R-S,S}(r)\right )$$

II. $$\left\{t \mid t \in \pi_{R-S} (r) \wedge \forall u \in s \left(\exists v \in r \left(u = v[S] \wedge t = v\left[R-S\right]\right )\right )\right\}$$

III.$$\left\{t \mid t \in \pi_{R-S} (r) \wedge \forall v \in r \left(\exists u \in s \left(u = v[S] \wedge t = v\left[R-S\right]\right )\right ) \right\}$$

IV. Select R.a, R.b
    From R, S
    Where R.c = S.c
Which of the above queries are equivalent?
A
I and II
B
I and III
C
II and IV
D
III and IV
GATE CSE Subjects
Software Engineering
Web Technologies
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12