1
GATE CSE 1996
Subjective
+2
-0
The concurrent programming constructs fork and join are as below: Fork (label) which creates a new process executing from the specified label join (variable) which decrements the specified synchronization variable (by 1) and terminates the process if the new value is not 0. Show the precedence graph for S1, S2, S3, S4 and S5 of the concurrent program below.
N = 2
M = 2
fork L3
fork L4
S1
L1 : join N
S3
L2: join M
S5
L3:S2
goto L1
L4:S4
goto L2
next:
2
GATE CSE 1992
MCQ (Single Correct Answer)
+2
-0.6
At a particular time of computation the value of a counting semaphore is 7. Then 20 P operations and 15 V operations were completed on this semaphore. The resulting value of the semaphore is:
A
42
B
2
C
7
D
12
3
GATE CSE 1990
Fill in the Blanks
+2
-0
Semaphore operations are atomic because they are implemented within the OS
4
GATE CSE 1987
MCQ (Single Correct Answer)
+2
-0.6
A critical region is:
A
One which is enclosed by a pair of P and V operations on semaphores
B
A program segment that has not been proved bug-free
C
A program segment that often causes unexpected system crashes
D
A program segment where shared resources are accessed
GATE CSE Subjects
Software Engineering
Web Technologies
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12