1
GATE EE 2002
MCQ (Single Correct Answer)
+2
-0.6
A generator is connected to a transformer which feeds another transformer through a short feeder. The zero sequence impedance values are expressed in pu on a common base and are indicated in figure. The Thevenin equivalent zero sequence impedance at point B is GATE EE 2002 Power System Analysis - Symmetrical Components and Symmetrical and Unsymmetrical Faults Question 29 English
A
0.8 + j0.6
B
0.75 + j0.22
C
0.75 + j0.25
D
1.5 + j0.25
2
GATE EE 2002
MCQ (Single Correct Answer)
+1
-0.3
Consider the problem of relay co-ordination for the distance relays $$R1$$ and $$R2$$ on adjacent lines of a transmission system figure. The Zone $$1$$ GATE EE 2002 Power System Analysis - Switch Gear and Protection Question 18 English
and Zone $$2$$ settings for both the relays are indicated on the diagram. Which of the following indicates the correct time setting for the Zone $$2$$ of relays $$R1$$ and $$R2.$$
A
$$TZ{2_{R1}} = 0.6s,\,\,TZ{2_{R2}} = 0.3s$$
B
$$TZ{2_{R1}} = 0.3s,\,\,TZ{2_{R2}} = 0.6s$$
C
$$TZ{2_{R1}} = 0.3s,\,\,TZ{2_{R2}} = 0.3s$$
D
$$TZ{2_{R1}} = 0.1s,\,\,TZ{2_{R2}} = 0.3s$$
3
GATE EE 2002
MCQ (Single Correct Answer)
+1
-0.3
Consider a power system with three identical generators. The transmission losses are negligible. One generator ($$G1$$) has a speed governor which maintains its speed constant at the rated value, while the other generators ($$G2$$ and $$G3$$) have governors with a droop of $$5$$%. If the load of the system is increased, then in steady state.
A
Generation of $$G2$$ and $$G3$$ is increased equally while generation of $$G1$$ is unchanged.
B
Generation of $$G1$$ alone is increased while generation of $$G2$$ and $$G3$$ is unchanged.
C
Generation of $$G1, G2$$ and $$G3$$ is increased equally.
D
Generation of $$G1, G2$$ and $$G3$$ is increased in the ratio $$0.5:25:0.25.$$
4
GATE EE 2002
MCQ (Single Correct Answer)
+2
-0.6
A power system consists of 2 areas (Area 1 and Area 2) connected by a single tie line (figure). It is required to carry out a load flow study on this system. While entering the network data, the tie-line data (connectivity and parameters) is inadvertently left out. If the load flow program is run with this incomplete data. GATE EE 2002 Power System Analysis - Load Flow Studies Question 17 English
A
The load-flow will converge only if the slack bus is specified in Area 1
B
The load-flow will converge only if the slack bus is specified in Area 2
C
The load-flow will converge if the slack bus is specified in either Area 1 or Area 2
D
The load-flow will not converge if only one slack bus is specified.
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12