1
GATE EE 2002
MCQ (Single Correct Answer)
+2
-0.6
A power system consists of 2 areas (Area 1 and Area 2) connected by a single tie line (figure). It is required to carry out a load flow study on this system. While entering the network data, the tie-line data (connectivity and parameters) is inadvertently left out. If the load flow program is run with this incomplete data. GATE EE 2002 Power System Analysis - Load Flow Studies Question 19 English
A
The load-flow will converge only if the slack bus is specified in Area 1
B
The load-flow will converge only if the slack bus is specified in Area 2
C
The load-flow will converge if the slack bus is specified in either Area 1 or Area 2
D
The load-flow will not converge if only one slack bus is specified.
2
GATE EE 2002
MCQ (Single Correct Answer)
+1
-0.3
Consider a power system with three identical generators. The transmission losses are negligible. One generator ($$G1$$) has a speed governor which maintains its speed constant at the rated value, while the other generators ($$G2$$ and $$G3$$) have governors with a droop of $$5$$%. If the load of the system is increased, then in steady state.
A
Generation of $$G2$$ and $$G3$$ is increased equally while generation of $$G1$$ is unchanged.
B
Generation of $$G1$$ alone is increased while generation of $$G2$$ and $$G3$$ is unchanged.
C
Generation of $$G1, G2$$ and $$G3$$ is increased equally.
D
Generation of $$G1, G2$$ and $$G3$$ is increased in the ratio $$0.5:25:0.25.$$
3
GATE EE 2002
MCQ (Single Correct Answer)
+1
-0.3
Consider the problem of relay co-ordination for the distance relays $$R1$$ and $$R2$$ on adjacent lines of a transmission system figure. The Zone $$1$$ GATE EE 2002 Power System Analysis - Switch Gear and Protection Question 19 English
and Zone $$2$$ settings for both the relays are indicated on the diagram. Which of the following indicates the correct time setting for the Zone $$2$$ of relays $$R1$$ and $$R2.$$
A
$$TZ{2_{R1}} = 0.6s,\,\,TZ{2_{R2}} = 0.3s$$
B
$$TZ{2_{R1}} = 0.3s,\,\,TZ{2_{R2}} = 0.6s$$
C
$$TZ{2_{R1}} = 0.3s,\,\,TZ{2_{R2}} = 0.3s$$
D
$$TZ{2_{R1}} = 0.1s,\,\,TZ{2_{R2}} = 0.3s$$
4
GATE EE 2002
MCQ (Single Correct Answer)
+2
-0.6
A generator is connected to a transformer which feeds another transformer through a short feeder. The zero sequence impedance values are expressed in pu on a common base and are indicated in figure. The Thevenin equivalent zero sequence impedance at point B is GATE EE 2002 Power System Analysis - Symmetrical Components and Symmetrical and Unsymmetrical Faults Question 30 English
A
0.8 + j0.6
B
0.75 + j0.22
C
0.75 + j0.25
D
1.5 + j0.25
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12