1
NEET 2022 Phase 1
MCQ (Single Correct Answer)
+4
-1
Change Language

An electric lift with a maximum load of 2000 kg (lift + passengers) is moving up with a constant speed of 1.5 ms$$-$$1. The frictional force opposing the motion is 3000 N. The minimum power delivered by the motor to the lift in watts is : (g = 10 ms$$-$$2)

A
23000
B
20000
C
34500
D
23500
2
NEET 2022 Phase 1
MCQ (Single Correct Answer)
+4
-1
Change Language

The energy that will be ideally radiated by a 100 kW transmitter in 1 hour is

A
36 $$\times$$ 107 J
B
36 $$\times$$ 104 J
C
36 $$\times$$ 105 J
D
1 $$\times$$ 105 J
3
NEET 2021
MCQ (Single Correct Answer)
+4
-1
Change Language
A particle is released from height S from the surface of the Earth. At a certain height its kinetic energy is three times its potential energy. The height from the surface of earth and the speed of the particle at that instant are respectively -
A
$${S \over 4},\sqrt {{{3gS} \over 2}} $$
B
$${S \over 4},{{3gS} \over 2}$$
C
$${S \over 4},{{\sqrt {3gS} } \over 2}$$
D
$${S \over 2},{{\sqrt {3gS} } \over 2}$$
4
NEET 2021
MCQ (Single Correct Answer)
+4
-1
Change Language
Water falls from a height of 60m at the rate of 15 kg/s to operate a turbine. The losses due to frictional force are 10% of the input energy. How much power is generated by the turbine? (g = 10 m/s2)
A
7.0 kW
B
10.2 kW
C
8.1 kW
D
12.3 kW
NEET Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12