The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below the arrows. GATE CE 2016 Set 2 Construction Material and Management - Critical Path Method Question 2 English The critical duration for this construction project is
A
13 days
B
14 days
C
15 days
D
16 days