GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The activity-on-arrow network of activities for a construction project is shown in the figure.
The durations (expressed in days) of the activities are mentioned below the arrows.
The critical duration for this construction project is