1
GATE CE 2022 Set 2
Numerical
+2
-0
The activities of a project are given in the following table along with their durations and dependency.
Activities | Duration (day) | Depends on |
---|---|---|
A | 10 | - |
B | 12 | - |
C | 15 | A |
D | 14 | B |
E | 10 | B, C |
The total float of the activity E (in day) is _________. (in integer)
Your input ____
2
GATE CE 2017 Set 1
Numerical
+2
-0
The activity details of a project are given below:
The estimated minimum time (in days) for the completion of the project will be________
Your input ____
3
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The activity-on-arrow network of activities for a construction project is shown in the figure.
The durations (expressed in days) of the activities are mentioned below the arrows.
The critical duration for this construction project is
Questions Asked from Critical Path Method (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE CE Subjects
Construction Material and Management
Geomatics Engineering Or Surveying
Levelling Traversing Theodolites and Plane Table Surveying Measurement of Area, Volume and Theory of Errors and Survey Adjustment Field Astronomy and Photogrammetric Surveying Basics of GIS, GPS and Remote Sensing Angular Measurements and Compass Survey Basic Concepts Linear Measurements and Chain Survey
Engineering Mechanics
Hydrology
Transportation Engineering
Strength of Materials Or Solid Mechanics
Reinforced Cement Concrete
Steel Structures
Environmental Engineering
Engineering Mathematics
Structural Analysis
Geotechnical Engineering
Origin of Soils Definitions and Properties of Soils Classification of Soils and Clay Mineralogy Effective Stress and Permeability Seepage Analysis Compaction of Soil Compressibility and Consolidation Shear Strength of Soil Stress Distribution of Soil Retaining Wall and Earth Pressure Stability of Slopes Shallow Foundation Pile Foundation Soil Stabilization
Fluid Mechanics and Hydraulic Machines
General Aptitude