Program Evolution Review Technique · Construction Material and Management · GATE CE
Start PracticeMarks 1
GATE CE 2024 Set 2
Consider the following data for a project of 300 days duration.Budgeted Cost of Work Scheduled (BCWS) = Rs. 200Budgeted Cost of Work Performed (BCWP) ...
GATE CE 2024 Set 1
Consider the statements P and Q.P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.Q: Client’s D...
GATE CE 2017 Set 2
For a construction project. The mean and standard deviation of the completion time are 200
days and 6.1 days, respectively. Assume normal distribution...
Marks 2
GATE CE 2016 Set 1
The Optimistic Time (O), most likely Time (M) and Pessimistic Time (P) (in days) of
the activities in the critical path are given below in the format ...