Consider the following data for a project of 300 days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCWP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190
The ‘schedule variance’ for the project is
GATE CE 2024 Set 2
2
Consider the statements P and Q.
P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.
Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.
Which one of the following options is CORRECT?
GATE CE 2024 Set 1
3
For a construction project. The mean and standard deviation of the completion time are 200
days and 6.1 days, respectively. Assume normal distribution and use the value of standard
normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days)
for the completion of the project would be __________.
GATE CE 2017 Set 2