Program Evolution Review Technique · Construction Material and Management · GATE CE

Start Practice

Marks 1

GATE CE 2024 Set 2
Consider the following data for a project of 300 days duration.Budgeted Cost of Work Scheduled (BCWS) = Rs. 200Budgeted Cost of Work Performed (BCWP) ...
GATE CE 2024 Set 1
Consider the statements P and Q.P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.Q: Client’s D...
GATE CE 2017 Set 2
For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution...

Marks 2

GATE CE 2016 Set 1
The Optimistic Time (O), most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format ...
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12