The figure shows a network diagram for a construction project. The activities $\mathrm{A}, \mathrm{B}, \mathrm{C}$, D, E, and F are represented by arrows and their durations are in the figure.
The total float available for the activity E in day(s) is equal to _________ (round off to the nearest integer).

A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the statements P and Q.
P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day.
Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.
Which one of the following options is CORRECT?
The table shows the activities and their durations and dependencies in a project.
| Activity | Duration (Days) | Depends on |
|---|---|---|
| A | 8 | - |
| B | 4 | A |
| C | 4 | B |
| D | 4 | C, L |
| F | 4 | A |
| G | 4 | F |
| H | 6 | G, L |
| K | 10 | A |
| L | 6 | F, K |
The total duration (in days) of the project is __________ (in integer).
The activities of a project are given in the following table along with their durations and dependency.
| Activities | Duration (day) | Depends on |
|---|---|---|
| A | 10 | - |
| B | 12 | - |
| C | 15 | A |
| D | 14 | B |
| E | 10 | B, C |
The total float of the activity E (in day) is _________. (in integer)
GATE CE Subjects
Browse all chapters by subject