Critical Path Method · Construction Material and Management · GATE CE
Start PracticeMarks 1
GATE CE 2024 Set 2
Consider the statements P and Q. P: In a Pure project organization, the project manager maintains complete authority and has maximum control over the ...
GATE CE 2022 Set 1
The project activities are given in the following table along with the duration and dependency.
.tg {border-collapse:collapse;border-spacing:0;}
.tg...
GATE CE 2016 Set 2
A construction project consists of twelve activities. The estimated duration (in days) required
to complete each of the activities along with the corr...
Marks 2
GATE CE 2024 Set 2
A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 day...
GATE CE 2024 Set 2
The table shows the activities and their durations and dependencies in a project.table { width: 100%; border-collapse: collapse; margin: 20px 0; } th ...
GATE CE 2022 Set 2
The activities of a project are given in the following table along with their durations and dependency.
.tg {border-collapse:collapse;border-spacing...
GATE CE 2017 Set 1
The activity details of a project are given below:
The estimated minimum time (in days) for the completion of the project will be________...
GATE CE 2016 Set 2
The activity-on-arrow network of activities for a construction project is shown in the figure.
The durations (expressed in days) of the activities are...