Critical Path Method · Construction Material and Management · GATE CE

Start Practice

Marks 1

GATE CE 2024 Set 2
Consider the statements P and Q. P: In a Pure project organization, the project manager maintains complete authority and has maximum control over the ...
GATE CE 2022 Set 1
The project activities are given in the following table along with the duration and dependency. .tg {border-collapse:collapse;border-spacing:0;} .tg...
GATE CE 2016 Set 2
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corr...

Marks 2

GATE CE 2024 Set 2
A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 day...
GATE CE 2024 Set 2
The table shows the activities and their durations and dependencies in a project.table { width: 100%; border-collapse: collapse; margin: 20px 0; } th ...
GATE CE 2022 Set 2
The activities of a project are given in the following table along with their durations and dependency. .tg {border-collapse:collapse;border-spacing...
GATE CE 2017 Set 1
The activity details of a project are given below: The estimated minimum time (in days) for the completion of the project will be________...
GATE CE 2016 Set 2
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are...
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12