The length of a baseline measured on ground at an elevation of 300m above mean sea level is 2250 m. The required correction to reduce to sea level len...
GATE CE 1990
The required slope correction for a length of 60m, along a gradient of 1 in 20 is
Marks 2
GATE CE 2024 Set 2
Differential levelling is carried out from point P (BM: +200.000 m) to point R. The readings taken are given in the table.