1
GATE CE 2024 Set 2
MCQ (Single Correct Answer)
+2
-0.833

A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the statements P and Q.

P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day.

Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.

Which one of the following options is CORRECT?

A

Both P and Q are TRUE

B

P is TRUE and Q is FALSE

C

Both P and Q are FALSE

D

P is FALSE and Q is TRUE

2
GATE CE 2024 Set 2
Numerical
+2
-0

The table shows the activities and their durations and dependencies in a project.

ActivityDuration (Days)Depends on
A8-
B4A
C4B
D4C, L
F4A
G4F
H6G, L
K10A
L6F, K

The total duration (in days) of the project is __________ (in integer).

Your input ____
3
GATE CE 2022 Set 2
Numerical
+2
-0

The activities of a project are given in the following table along with their durations and dependency.

Activities Duration (day) Depends on
A 10 -
B 12 -
C 15 A
D 14 B
E 10 B, C

The total float of the activity E (in day) is _________. (in integer)

Your input ____
4
GATE CE 2017 Set 1
Numerical
+2
-0
The activity details of a project are given below: GATE CE 2017 Set 1 Construction Material and Management - Critical Path Method Question 6 English The estimated minimum time (in days) for the completion of the project will be________
Your input ____
GATE CE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12