1
GATE CE 2024 Set 2
MCQ (Single Correct Answer)
+2
-0.833

A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the statements P and Q.

P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day.

Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.

Which one of the following options is CORRECT?

A

Both P and Q are TRUE

B

P is TRUE and Q is FALSE

C

Both P and Q are FALSE

D

P is FALSE and Q is TRUE

2
GATE CE 2024 Set 2
Numerical
+2
-0

The table shows the activities and their durations and dependencies in a project.

ActivityDuration (Days)Depends on
A8-
B4A
C4B
D4C, L
F4A
G4F
H6G, L
K10A
L6F, K

The total duration (in days) of the project is __________ (in integer).

Your input ____
3
GATE CE 2022 Set 2
Numerical
+2
-0

The activities of a project are given in the following table along with their durations and dependency.

Activities Duration (day) Depends on
A 10 -
B 12 -
C 15 A
D 14 B
E 10 B, C

The total float of the activity E (in day) is _________. (in integer)

Your input ____
4
GATE CE 2017 Set 1
Numerical
+2
-0
The activity details of a project are given below: GATE CE 2017 Set 1 Construction Material and Management - Critical Path Method Question 7 English The estimated minimum time (in days) for the completion of the project will be________
Your input ____