1
GATE CE 2017 Set 1
Numerical
+2
-0
The activity details of a project are given below:
The estimated minimum time (in days) for the completion of the project will be________

Your input ____
2
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The activity-on-arrow network of activities for a construction project is shown in the figure.
The durations (expressed in days) of the activities are mentioned below the arrows.
The critical duration for this construction project is

Questions Asked from Critical Path Method (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE CE Subjects
Construction Material and Management
Geomatics Engineering Or Surveying
Engineering Mechanics
Transportation Engineering
Strength of Materials Or Solid Mechanics
Reinforced Cement Concrete
Steel Structures
Environmental Engineering
Engineering Mathematics
Structural Analysis
Geotechnical Engineering
Fluid Mechanics and Hydraulic Machines
General Aptitude