The activity details of a project are given below:
The estimated minimum time (in days) for the completion of the project will be________
![GATE CE 2017 Set 1 Construction Material and Management - Critical Path Method Question 4 English](https://gateclass.cdn.examgoal.net/examside/questions/4d99673910b4c4fcddf0b94a616604fd9682964b7a154cf08c183c386fbab9c2.jpg)
Your input ____
2
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The activity-on-arrow network of activities for a construction project is shown in the figure.
The durations (expressed in days) of the activities are mentioned below the arrows.
The critical duration for this construction project is
![GATE CE 2016 Set 2 Construction Material and Management - Critical Path Method Question 5 English](https://gateclass.cdn.examgoal.net/examside/questions/84a76c892a9493071c351d76c39605a2f34601738d8561aa8950e7d35ffad430.jpg)
Questions Asked from Critical Path Method (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE CE Subjects
Engineering Mechanics
Strength of Materials Or Solid Mechanics
Structural Analysis
Construction Material and Management
Reinforced Cement Concrete
Steel Structures
Geotechnical Engineering
Fluid Mechanics and Hydraulic Machines
Geomatics Engineering Or Surveying
Environmental Engineering
Transportation Engineering
Engineering Mathematics
General Aptitude