The table shows the activities and their durations and dependencies in a project.

ActivityDuration (Days)Depends on
A8-
B4A
C4B
D4C, L
F4A
G4F
H6G, L
K10A
L6F, K

The total duration (in days) of the project is __________ (in integer).

Your input ____
2
GATE CE 2022 Set 2
Numerical
+2
-0

The activities of a project are given in the following table along with their durations and dependency.

Activities Duration (day) Depends on
A 10 -
B 12 -
C 15 A
D 14 B
E 10 B, C

The total float of the activity E (in day) is _________. (in integer)

Your input ____
3
GATE CE 2017 Set 1
Numerical
+2
-0
The activity details of a project are given below: GATE CE 2017 Set 1 Construction Material and Management - Critical Path Method Question 7 English The estimated minimum time (in days) for the completion of the project will be________
Your input ____
4
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below the arrows. GATE CE 2016 Set 2 Construction Material and Management - Critical Path Method Question 8 English The critical duration for this construction project is
A
13 days
B
14 days
C
15 days
D
16 days
GATE CE Subjects
EXAM MAP