1
GATE CE 2024 Set 2
Numerical
+2
-0.833

The table shows the activities and their durations and dependencies in a project.

ActivityDuration (Days)Depends on
A8-
B4A
C4B
D4C, L
F4A
G4F
H6G, L
K10A
L6F, K

The total duration (in days) of the project is __________ (in integer).

Your input ____
2
GATE CE 2022 Set 2
Numerical
+2
-0.67

The activities of a project are given in the following table along with their durations and dependency.

Activities Duration (day) Depends on
A 10 -
B 12 -
C 15 A
D 14 B
E 10 B, C

The total float of the activity E (in day) is _________. (in integer)

Your input ____
3
GATE CE 2017 Set 1
Numerical
+2
-0
The activity details of a project are given below: GATE CE 2017 Set 1 Construction Material and Management - Critical Path Method Question 6 English The estimated minimum time (in days) for the completion of the project will be________
Your input ____
4
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below the arrows. GATE CE 2016 Set 2 Construction Material and Management - Critical Path Method Question 7 English The critical duration for this construction project is
A
13 days
B
14 days
C
15 days
D
16 days
GATE CE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12