1
GATE CE 2024 Set 1
MCQ (Single Correct Answer)
+1
-0.33

Consider the statements P and Q.

P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.

Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.

Which one of the following options is CORRECT?

A

Both P and Q are TRUE

B

P is TRUE and Q is FALSE

C

Both P and Q are FALSE

D

P is FALSE and Q is TRUE

2
GATE CE 2017 Set 2
Numerical
+1
-0
For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________.
Your input ____
GATE CE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12