1
GATE CE 2024 Set 2
MCQ (Single Correct Answer)
+1
-0.33

Consider the following data for a project of 300 days duration.

Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCWP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190

The ‘schedule variance’ for the project is

A

(−)Rs. 50

B

(−)50 days

C

(+)Rs. 50

D

(+)50 days

2
GATE CE 2024 Set 1
MCQ (Single Correct Answer)
+1
-0.33

Consider the statements P and Q.

P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.

Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.

Which one of the following options is CORRECT?

A

Both P and Q are TRUE

B

P is TRUE and Q is FALSE

C

Both P and Q are FALSE

D

P is FALSE and Q is TRUE

3
GATE CE 2017 Set 2
Numerical
+1
-0
For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________.
Your input ____