1
GATE EE 2005
MCQ (Single Correct Answer)
+2
-0.6
At an industrial sub-station with a $$4$$ $$MW$$ load, a capacitor of $$2$$ MVAR is installed to maintain the load power factor at $$0.97$$ lagging. If the capacitor goes out of service, the load power factor becomes
A
$$0.85$$ lag
B
$$1.00$$ lag
C
$$0.80$$ lag
D
$$0.90$$ lag
2
GATE EE 2005
MCQ (Single Correct Answer)
+1
-0.3
The insulation strength of an EHV transmission line is mainly governed by
A
Load power factor
B
Switching over-voltages
C
Harmonics
D
Corona
3
GATE EE 2005
MCQ (Single Correct Answer)
+2
-0.6
For the triangular waveform shown in the figure, the $$RMS$$ value of the voltage is equal to GATE EE 2005 Signals and Systems - Continuous Time Periodic Signal Fourier Series Question 7 English
A
$$\sqrt {{1 \over 6}} $$
B
$$\sqrt {{1 \over 3}} $$
C
$${1 \over 3}$$
D
$$\sqrt {{2 \over 3}} $$
4
GATE EE 2005
MCQ (Single Correct Answer)
+2
-0.6
If u(k) is the unit step and $$\delta\left(k\right)$$ is the unit impulse function, the inverse z-transform of $$F\left(z\right)=\frac1{z+1}$$ for k>0 is:
A
$$\left(-1\right)^k\delta\left(k\right)$$
B
$$\delta\left(k\right)-\left(-1\right)^k$$
C
$$\left(-1\right)^ku\left(k\right)$$
D
$$u\left(k\right)-\left(-1\right)^k$$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12