1
GATE CE 2016 Set 1
Numerical
+2
-0
The Optimistic Time (O), most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P. GATE CE 2016 Set 1 Construction Material and Management - Program Evolution Review Technique Question 3 English The expected completion time (in days) of the project is _______.
Your input ____