1
GATE CE 2016 Set 1
Numerical
+2
-0
The Optimistic Time (O), most likely Time (M) and Pessimistic Time (P) (in days) of
the activities in the critical path are given below in the format O-M-P.
The expected completion time (in days) of the project is _______.

Your input ____
Questions Asked from Program Evolution Review Technique (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE CE Subjects
Engineering Mechanics
Strength of Materials Or Solid Mechanics
Structural Analysis
Construction Material and Management
Reinforced Cement Concrete
Steel Structures
Geotechnical Engineering
Fluid Mechanics and Hydraulic Machines
Geomatics Engineering Or Surveying
Environmental Engineering
Transportation Engineering
Engineering Mathematics
General Aptitude