GATE CE 2025 Set 1
MCQ (More than One Correct Answer)
+2
-0

In the context of construction project management, which of the following statements is/are true:

A
A dummy activity will consume time and resources
B
The programme evaluation and review technique (PERT) is best suited for projects with large uncertainties in the duration of activities
C
A Gantt chart is commonly used for identifying the 'critical path' of activities in a project
D
Free float is the amount of time by which the start of an activity can be delayed without causing a delay in the start of a following activity
2
GATE CE 2016 Set 1
Numerical
+2
-0
The Optimistic Time (O), most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P. GATE CE 2016 Set 1 Construction Material and Management - Program Evolution Review Technique Question 4 English The expected completion time (in days) of the project is _______.
Your input ____