GATE CE 2022 Set 1
MCQ (Single Correct Answer)
+1
-0.33
The project activities are given in the following table along with the duration and dependency.
| Activities | Duration (days) | Depends on |
|---|---|---|
| P | 10 | - |
| Q | 12 | - |
| R | 5 | P |
| S | 10 | Q |
| T | 10 | P, Q |
Which one of the following combinations is correct?
2
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A construction project consists of twelve activities. The estimated duration (in days) required
to complete each of the activities along with the corresponding network diagram is shown
below.
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,GATE CE Subjects
Browse all chapters by subject
Structural Analysis
Fluid Mechanics and Hydraulic Machines
Strength of Materials Or Solid Mechanics
Reinforced Cement Concrete
Construction Material and Management
Geotechnical Engineering
Origin of Soils Definitions and Properties of Soils Classification of Soils and Clay Mineralogy Effective Stress and Permeability Seepage Analysis Compaction of Soil Compressibility and Consolidation Shear Strength of Soil Stress Distribution of Soil Retaining Wall and Earth Pressure Stability of Slopes Shallow Foundation Pile Foundation Soil Stabilization
General Aptitude
Environmental Engineering
Steel Structures
Hydrology
Transportation Engineering
Engineering Mathematics
Engineering Mechanics
Geomatics Engineering Or Surveying
Levelling Theodolites and Plane Table Surveying Curves Field Astronomy and Photogrammetric Surveying Traversing Measurement of Area, Volume and Theory of Errors and Survey Adjustment Basics of GIS, GPS and Remote Sensing Basic Concepts Linear Measurements and Chain Survey Angular Measurements and Compass Survey